WORKDAY (start_date,days,holidays)


where,

  • represents the starting date,
  • Failed to parse (MathML with SVG or PNG fallback (recommended for modern browsers and accessibility tools): Invalid response ("Math extension cannot connect to Restbase.") from server "https://wikimedia.org/api/rest_v1/":): {\displaystyle days} represents the number of nonweekend and nonholiday days before or after the starting date, and
  • Failed to parse (MathML with SVG or PNG fallback (recommended for modern browsers and accessibility tools): Invalid response ("Math extension cannot connect to Restbase.") from server "https://wikimedia.org/api/rest_v1/":): {\displaystyle holidays} is an optional list of one or more dates to exclude from the working days.
    • WORKDAY() displays the working day before or after the mentioned number of days from the starting date, excluding the weekend days and holidays.

Description

WORKDAY(start_date, days, holidays)

  • Failed to parse (MathML with SVG or PNG fallback (recommended for modern browsers and accessibility tools): Invalid response ("Math extension cannot connect to Restbase.") from server "https://wikimedia.org/api/rest_v1/":): {\displaystyle start-date} and Failed to parse (MathML with SVG or PNG fallback (recommended for modern browsers and accessibility tools): Invalid response ("Math extension cannot connect to Restbase.") from server "https://wikimedia.org/api/rest_v1/":): {\displaystyle holidays} should be entered either in 'date format' or 'dates returned using formulas'.
  • If date values are invalid, Calci displays #N/A error message.
  • Argument Failed to parse (MathML with SVG or PNG fallback (recommended for modern browsers and accessibility tools): Invalid response ("Math extension cannot connect to Restbase.") from server "https://wikimedia.org/api/rest_v1/":): {\displaystyle days} can be positive or negative.
  • For positive days, Calci calculates working day after the mentioned number of days from starting date. For negative days, Calci calculates the working day before the mentioned days from the starting date.
  • We can use Range values also. For Example: WORKDAY(#1/6/2013-3/6/2013,7).
  • #date notation needs mm/dd/yy format .

Examples

Consider the following example that shows starting dates in cells A1, B1. Holidays are listed in cells A3 and A4.

6/1/2014 3/1/2014
140 -30
8/4/2014
9/30/2014
=WORKDAY(A1,A2): Calculates next working day 140 days after date mentioned in A1. 
Weekend days are excluded. Displays 12/12/2014 as a result. =WORKDAY(A1,A2,A3:A4):Calculates next working day 140 days after date mentioned in A1
and holidays in A3, A4. Weekend days are excluded.
Displays 12/16/2014 as a result. =WORKDAY(B1,B2) : Calculates working day 30 days before the starting date mentioned in B1.
Displays 01/20/2014 as a result. =WORKDAY(DATE(2013,6,1),60): Calculates next working day 60 days after mentioned date.
Displays 8/23/2013 as a result.