Manuals/calci/NETWORKDAYS

Revision as of 13:36, 9 July 2018 by Devika (talk | contribs)

NETWORKDAYS(start_date, end_date, holidays)

NETWORKDAYS (start_date,end_date,holidays)


where,

  • start_date represents the starting date,
  • end_date represents the end date, and
  • holidays is an optional range of one or more dates to exclude from the working days.

NETWORKDAYS() returns the number of whole workdays between two dates.

Description

NETWORKDAYS(start_date, end_date, holidays)

  • start_date, end_date and holidays should be entered either in 'date format' or 'dates returned using formulas'.
  • If date values are invalid, Calci displays #NULL error message.
  • We can use the DD/MM/YYYY format also. For Example:"14/5/2005[DD/MM/YYYY]".
  • We can use Range values also. For Example: NETWORKDAYS(DATE(2012,6,1),#12/31/2012-12/31/2013)
  • #date notation needs mm/dd/yy format .

Examples

Consider the following example that shows the use of NETWORKDAYS function:

6/1/2013
7/30/2013
7/1/2013
7/13/2013
=NETWORKDAYS(A1,A2): Calculates working days in the range of cells A1 and A2. Weekend days are excluded. 
Displays 42 as a result. =NETWORKDAYS(A1,A2,A3): Calculates working days in the range of cells A1 and A2 and a holiday in A3.
Weekend days are excluded. Displays 41 as a result. =NETWORKDAYS(A1,A2,A3:A4):Calculates working days in the range of cells A1 and A2 and holidays in A3, A4.
Weekend days are excluded, A4 is overlapped with weekend day. Displays 41 as a result. =NETWORKDAYS(DATE(2012,6,1),DATE(2012,12,31)): Calculates working days between two mentioned dates.
Displays 152 as a result.