XNPV(R, V, dates)

Where 'rate' is the discount rate to apply to the cash flows, 'V' is a series of cash flows that corresponds to a schedule of payments in dates and 'dates' is a schedule of payment dates.


 

This function computes the net present value for a schedule of cash flows that is not essentially periodic.


 
  • The arguments should be numerics.
  • XNPV shows the error value whenever any number in dates precedes the starting date or values and dates contain a different number of values.
  • XNPV is calculated as follows:

where:

di = the ith payment date, d1 = the 0th payment date and Pi = the ith payment.


XNPV


 

Lets see an example,

XNPV(R, V, dates)

B C

-10000 02-01-2009

3000 04-01-2009

4300 11-30-2009

3250 03-15-2010

2200 05-01-2010

=XNPV(.07,B2:B6,C2:C6) is 2069.5268 '


Syntax

Remarks

Examples

Description

Column1 Column2 Column3 Column4
Row1 -10000 02-01-2009 2069.5268
Row2 3000 04-01-2009
Row3 4300 11-30-2009
Row4 3250 03-15-2010
Row5 2200 05-01-2010
Row6
Row7